New Water Treatment Plant

  • Water Treatment Plant
    1. Daris Contractors is the Contractor
    2. Notice to Proceed on 16 March 2020
    3. Finish date June 9, 2021
    4. Pouring walls for the Process Building -60% completed
    5. Pour pipe gallery slab for the sludge backwash pump station – 60% completed Start working on the Chemical Building foundation – 5% completed
    6. Began dirt work for the lab building – 20% completed

September 30, 2020 - Work continues on the building of the new Water Treatment Plant in Collinsville.  The over 8 million dollar project began in March 2020.  Assistant City Manager of Operations, Craig Stokes reports that the work is progressing on time if not a little ahead of schedule.  Weather permitting through the winter months, the new processing section of the plant should be finished in April of 2021 with the whole new facility completed and fully operational by June or July of next year. 

March 16, 2020- Ground Breaking Event for new Water Treatment Plant (Canceled due to ran.)

January 28, 2020 - Nearly 6 months ahead of schedule, the City of Collinsville will be awarding the contract to the best, low bid for construction of the new water treatment plant at the Monday, February 3, 2020, City Council Meeting. Five bids were received and after careful evaluation the most suitable plan will be presented to the City Council for approval at the 5:30 p.m. meeting. With oversight from the City Council and weather permitting, new construction is expected to begin within 45 days. The new water treatment plant should be completed in late summer 2021. Stay connected to the City of Collinsville Facebook page and City website for updates as they are made available. 

September 3, 2019

In the spring of 2018, the City Commission approved engineering services to Holloway, Updike and Bellen for a new water treatment plant. Plans and specs have been developed and are going through the final refining stage now.

In addition to plans for our new Water Plant we are in the process developing plans to loop our water system line for circulation of the water.

City administration has met with ODEQ and financial advisors to review the plans and proposed timeline which is outlined below.

Water Treatment Plant Timeline

Collinsville Water Treatment Plant Nov 1, 2018 Oct 1, 2021

Update Engineering Report for New Plant Nov 1, 2018 Jan 31, 2019

Engineering Report Approval Feb 1, 2019 Feb 28, 2019

Preliminary Plans Dec 1, 2018 April 1, 2019

Collinsville Review April 2, 2019 May 1, 2019

Final Plans May 2, 2019 Dec 14, 2019

ODEQ Review/Collinsville Review Dec 15, 2019 Feb 15, 2020

Bidding/Contracting Mar 15, 2020 June 1, 2020

Construction July 1, 2020 Oct 1, 2021

Please know that your City Commission and administration are and have been working on the new water treatment plant plans. A project of this magnitude takes time and has to be approved by several entities including ODEQ, OWRB, financial advisors, and the City. Please bear with us through this project. We will have a new water treatment plant soon.

Thank you,

Pam Polk

City Manager